This document from: http://www.ext.vt.edu/pubs/mines/460-130/460-130.html
Powell River Project Reclamation Guidelines for Surface-Mined Land
in Southwest Virginia
Stabilizing Reclaimed Mines to Support Buildings and Development
Authors: Carl E. Zipper, Extension Specialist, Department of Crop and Soil
Environmental Sciences, and Associate Director, Powell River Project, Virginia
Tech; and Steven Winter, Professional Engineer, Schnabel Engineering Associates,
Blacksburg, Virginia
Publication Number 460-130, Posted July 1997
Land use constraints hinder economic activity in the Virginia coalfield
region; lack of flat land hinders infrastructure construction, industrial
recruitment, and business development. Reclaimed coal mines are widely discussed
as potential development sites, but modern reclamation rarely prepares mined
areas for building-support purposes. This publication describes
mine-stabilization procedures that can be employed in developing reclaimed mine
areas for building construction.
This publication outlines general concepts and guidelines. Parties seeking to
construct buildings on any mined area should engage the services of a
professional engineer.
Background: Land Settlement and Structural Distortion A critical factor
affecting suitability of reclaimed mines for building construction is surface
stability. As filled lands, virtually all reclaimed mines will be subject to
some settlement, or consolidation, over time. Although it can damage utility
connections, uniform, even ground settlement of 2 inches or less will generally
cause little or no damage to most building types, "Differential settlement"
(where the depth of settlement varies under different parts of a structure) can
damage buildings through "structural distortion." Differential settlement is
common on reclaimed mines. Differential settlement occurs when significant
variations in depth, composition, or compaction are present in spoils underlying
a building site.
Rigid or semi-rigid structures
employing large volumes of concrete and structures covering large lateral areas
are particularly sensitive to distortion and damage due to differential
settlement.
It is especially important to construct lands that will minimize differential
settlement if an industrial use is intended for a reclaimed site. Industrial
facilities typically employ concrete floors covering large areas. High-value
manufacturing and processing operations typically require high levels of
mechanical precision; a shifting or cracking concrete floor will not be
compatible with such activities. Nonreinforced masonry structures will be
especially sensitive to settlement.
Mine Reclamation Procedures to Minimize Differential
SettlementReclaimed mines are best able to accommodate building
construction when building locations are identified prior to mining so that
reclamation procedures can be designed to produce a stabilized building site.
Spoil DepthBuildings should be located in areas where spoil depth is
relatively uniform. Ideally, buildings will also be placed in areas where
underlying spoil depth is relatively shallow. In a conventional contour mining
operation, building sites should be located over solid bench areas, not hollow
fills.
The reason for maintaining a uniform spoil depth under building locations is
that differential settlement is a condition that should be avoided. All
spoils will settle, regardless of placement procedures; depth of spoil will be a
major factor that influences amount of settlement. If spoil depths under a
building site are even and uniform, ground settlement is more likely to be even
and uniform. Locating a building site where spoils are of minimum practical
depth will reduce the costs of spoil-placement and site-stabilization procedures
if employed.
If only a portion of the reclaimed site will consist of shallow spoil over a
solid bench area, it is important to survey prior to spoil placement so the area
suitable for building construction can be located precisely after mining and
reclamation are complete.
Spoil PlacementSpoils underlying areas being prepared for building
construction should be placed in a controlled fashion. The spoil placement
procedures recommended below will be more costly than those typically employed
by Appalachian coal surface mines; they are intended to minimize
settlement-induced distortion of overlying building structures.
The following are factors that should be considered in developing a mine
reclamation plan for a site intended to support a high-value building:
A building-support "pad" should be constructed using controlled
spoil placement procedures.
A well-defined spoil "pad" should be carefully constructed under the planned
location of the building and its immediate surroundings using
controlled-placement procedures. The
pad should extend beyond the building's actual perimeter by at least 10 feet in
all directions. General guidelines for construction of the spoil pad follow, but
the actual procedure should be designed by a professional engineer who has
access to accurate data describing material properties and settlement
characteristics of available mine spoils. At the conclusion of pad construction,
the area should be surveyed so the pad's exact location can be identified after
reclamation is complete.
The building-support pad should be constructed through placement
of spoil in lifts of controlled thickness.
The ideal thickness of each lift will depend upon a variety of factors,
including physical factors such as the spoil's engineering characteristics and
the type of equipment available for spoil compaction. Other factors will include
total depth of spoils that will underlie the building, the length of time likely
to elapse between spoil placement and building construction, and the building's
design.
A lift thickness of about 1 - 2 feet will be sufficient to minimize
settlement in most situations, if that lift is thoroughly compacted. Achieving
this 1-to-2 foot lift thickness will not be economically feasible on most mines.
A 2-to-4 foot thickness, although not ideal, will achieve a reasonable level of
stability if compacted uniformly and if spoil composition is controlled. Mine
spoils with a composition dominated by hard sandstone spoils and rock fragments
will compact more effectively at 3-to-4 foot thicknesses than spoils with
composition dominated by shales and clays. If operational problems prevent spoil
placement in lifts that are 4 feet or less in thickness, use of controlled lifts
of minimum practical thickness (even if greater than 4 feet) and controlled
composition would be a superior practice to random dumping.
The composition of spoils in each lift of the building-support pad
should be carefully controlled.
Ideally, spoils within each lift should be of a single rock type, although
this may not be practical on some sites. If possible, use of rock fragments
larger than 1 foot in diameter should be avoided during construction of the
building-support pad. Use of a hard, competent material (such as durable-rock
sandstone) is preferred to use of rocks that will slake in water, such as most
siltstones and shales.
From a pure geotechnical standpoint, the best procedure to minimize
settlement would be to utilize a screening procedure so as to rigorously control
rock fragment size while building the support pad. This will not be a practical
option on most operating coal surface mines.
An alternative practice -- one that is not ideal from a geotechnical
standpoint, but is less costly -- will be to control spoil fragment size, as
well as rock type, of the building-support pad by exercising control over spoil
movement procedures. Under this practice, spoil excavation and movement
procedures would employ one or more alternate dumpsites that do not underlie
future building areas. If the spoil is being moved by truck, the truck operator
can be instructed to dump loads containing materials that are not suitable for
building support in an alternate dumpsite location, while suitable materials are
placed in the building-support fill.
The loader operator will be the person on most jobsites who has the best view
of the material in each truckload. The loader operator can be instructed to
direct spoil movement by communicating with the truck operators. Given a small
number of dumpsite locations, hand signals (viewed by the truck operator through
the rear view mirror), horn signals, or other means can be used by the loader
operator to direct spoil movement.
If mining economics prevent placement of material in compacted lifts of
controlled thickness, the stability of the postmining landform will be increased
if the composition of spoils placed in areas of potential building construction
is controlled. Use of hard-sandstone spoils and exclusion of siltstones and
shales in areas of potential building construction will enhance the postmining
stability of those areas, even if spoil is not placed in compacted lifts. If
this practice is followed, it will be important to document the location of
those lands constructed using hard sandstone spoils through a survey or other
means.
Each lift should be thoroughly compacted in place.
Special compaction equipment, such as a vibratory roller, may be employed to
achieve a thorough and uniform compaction of each lift. Such practice is
preferred from a geotechnical standpoint. However, use of specialized compaction
equipment will be cost prohibitive for most coal-mining operations.
An alternative method of achieving spoil compaction will be to use loaded
haul trucks. As loaded trucks drive over previously placed spoil to reach the
dumpsite, significant compaction will occur. The
challenge to the mine foreman will be to design a spoil placement sequence that
will cause compaction to occur as a result of routine spoil movement. Truck
drivers can be instructed to vary the location of each route so as to achieve
more-or-less uniform wheel coverage over the entire compaction area. If this
procedure is employed, it will be important to maintain consistent lift
thicknesses. Generally, the weight of a track dozer will not be sufficient to
compact spoil to a degree necessary to achieve a stabilized building support.
Mine spoils cannot be compacted effectively if they are extremely dry or
extremely wet. If a high-value building is to be constructed on the reclaimed
site, and the goal is to reduce postreclamation settlement to an absolute
minimum, spoil placement procedures should be designed with an engineer's input
so as to assure spoil-moisture contents that are optimal for compaction. The
optimum moisture content for compaction of most mine-spoils containing large
quantities of soil-sized materials will range from 5 to 15 percent.
On most operating surface mines, use of procedures to exert firm control over
spoil moisture contents during compaction will be cost-prohibitive. On eastern
U.S. mines, spoils in the field will rarely become too dry for effective
compaction; however, they can become too wet during damp weather. The effect of
compaction is to press the mineral particles close together, reducing pore
volumes and opportunity for further consolidation. When spoils are extremely
moist, water occupying the pores between small mineral particles effectively
limits the ability of the particles to be forced together. Therefore, it is
advisable to avoid placement and compaction of building-support pads during wet
weather whenever possible.
The building-site fill should be well drained.
A buildup of water in the fill can cause substantial settlement -- even if it
occurs many years after fill placement. Surface drainage, building
placement, the orientation and pitch of subsurface compaction planes, and the
placement of rock underdrains are factors which can help to prevent a buildup of
water in the fill. For example, construction of a building-support pad using
lifts that have slight crowns would be a superior practice to construction of
lift surfaces which drain inward. Large durable-rock fragments can be placed at
the base of those spoils that surround the building-support pads so as to assure
adequate drainage.
SummaryThe above procedures can minimize postreclamation settlement --
but they will not eliminate it. Settlement differentials of one inch or more can
have a substantial damaging effect on most building types.
When land is constructed using the above procedures, precautions remain in
order. After mine-fill construction is complete, some time should be allowed to
pass prior to building construction. Survey points should be established to
monitor postmining settlement; only when settlement has slowed to acceptable
levels should construction begin. Settlement will be most severe during the
first year following spoil placement.
Thorough documentation of procedures employed to construct the
building-support pad will aid future building and site design. Periodic visits
of a geotechnical engineer to the site during construction will be the best way
to provide that documentation. If the engineer who designs postmining site-usage
does not have precise knowledge of the procedures utilized to construct the
reclaimed landform, the resulting building/site design is likely to be more
conservative (and more costly) than necessary. If the engineer is able to come
on site periodically to observe controlled spoil-placement procedures and obtain
spoil samples, site-usage design can accommodate those spoil placement
procedures that did occur.
Building on Sites Prepared Using Conventional Spoil PlacementIn
Appalachia, common land-reclamation procedures do not make extensive use of
controlled spoil-placement procedures such as those described above.
Nonetheless, there will be opportunities to develop reclaimed mines, even when
the reclamation has not used optimal procedures.
Several options are available for building on settlement-prone reclaimed
mines. These are described below.
Allow the Site to StabilizeEventually, the passage of time will
stabilize virtually all reclaimed-mine sites. In some cases, construction of
small buildings has been successful on older mine sites, once enough time has
passed to allow the rate settlement to slow. In most cases, larger buildings on
spoils of significant depth that have not been compacted in place will require
site stabilization procedures.
Depth of settlement after the first year was calculated using
the formula
TS = A*H*(LogT1-LogT2)/100
where TS represents total settlement, H represents the fill height, and
T1 and T2
represent time after mining expressed in years (Krebs, 1987). A is a settlement
factor which varies with spoil composition. Figure 4 was constructed using a
settlement factor of 1.0 for loose siltstone, and 0.2 for compacted sandstone.
The sandstone settlement factor represents excellent compaction of material
placed in 1 to 2 foot lifts. Figure 4 shows that a 100-foot depth of loose
siltstone spoil would be likely to settle about 1 foot between the second and
tenth years after mining, and another foot in the 90 years after that. The
compacted sandstone fill would settle about one-fifth of these amounts.
These figures represent settlement of non-saturated spoils. If spoils become
saturated, due to a high water table or a concentration of surface water on the
site, more rapid settlement can be expected during and immediately following
saturation.
While Figure 4 represents total settlement, differential settlement is
what damages buildings. If the spoil in the building-support fill is relatively
uniform in physical characteristics and degree of compaction, settlement
differentials are likely to be only a fraction of the total settlement
represented in Figure 4.
If an expensive building design is to be employed, placement of survey stakes
and measurement of actual settlement through at least one winter season prior to
building would be desirable.
If settlement of the mine-fill surface is continuing, removal of surface
spoils to the depth of a design surcharge (see below) will expose spoils that
have been stabilized by the weight of overlying materials and may be suitable
for building, depending on the nature of the underlying material and the age of
fill.
Use a Building Design that Can Tolerate SettlementThis can be an option
for some structures, depending on the owner's intended use for the site. One
strategy would be to employ a building design that would be able to accommodate
distortion without losing functionality. Manufactured housing is typically able
to withstand distortion due to settlement better than site-built homes, because
of design features intended to help the building withstand the rigors of
transportation. Small, portable buildings (such as trailers) can be built with
accessible support points that will enable adjustment of supporting piers
through shimming or other means, if such an adjustment becomes necessary as a
response to differential settlement. Metal-shell buildings can
typically tolerate higher levels of distortion than many other building types.
Another strategy would be to use a rigid structure that is capable of
withstanding settlement of underlying ground. For relatively small buildings, a
prestressed concrete slab can be designed to "float" on the mine spoil surface,
bridging whatever voids may develop and remaining rigid despite any differential
settlement of underlying materials. Larger buildings can also make use of
prestressed slabs, but only with greater design difficulty and expense.
Nonreinforced masonry is poor in ability to withstand differential settlement
without fracturing. Concrete block is generally a poor choice for a construction
material on settlement-prone ground.
A third possible strategy would be to set piers or pilings through the mine
spoil. If the piers are strong enough to support the building and long enough to
reach undisturbed ground, they should provide a stable support despite any
settling of the mine spoils that underlie the building. Generally speaking,
drilling piling locations will be preferable to driving the pilings, especially
in a stony mine spoil. Pilings will be an expensive way to support buildings on
all but the thinnest mine spoils - where it may make greater economic sense to
excavate and replace underlying spoil than to place the building on pilings.
Employ Procedures to Stabilize the Building SiteIn cases where a stable
building support must be assured, it is possible to treat the spoil that has
been placed on the mining site in a manner that will increase the ground's
stability as underlying support for the building structure. Any one of several
methods may be used to achieve this goal.
Depending on spoil thickness, it may be possible to excavate spoil from
beneath the building's location; the spoil could then be replaced using
controlled placement and compaction procedures.
Another option would be to compact the inground spoil using mechanical
methods. Several procedures are available to achieve this goal. A procedure
called dynamic compaction employs a heavy weight that is dropped from a
specified height to compact the uppermost spoil layer in a repetitive grid-like
pattern. When prescribed, dynamic compaction is typically intended to achieve a
tightly-compacted "zone" of spoil constituting the upper 15 to 30 feet of the
fill. This tightly compacted zone is expected to remain rigid despite any
settling of the underlying noncompacted spoil, thus acting in a fashion similar
to the prestressed concrete slab described above.
Another method for achieving compaction and stabilization of the
building-support fill is called surcharge preloading. This procedure is carried
out by loading the building-support spoil with soil or mine spoil material. The
weight exerted by this mass (typically, more than the planned building) will
accelerate consolidation of underlying spoil. Settlement plates are placed on
the spoil surface prior to fill placement; these are horizontal metal plates
attached to vertical riser pipes that extend upward through the surface
material, allowing the rate of spoil settlement to be monitored with surveying
instruments. When the downward movement of the settlement plates slows to an
acceptable rate, the surcharge load is removed and the building site is prepared
for construction.
On sites that are more than 2 years old, a less costly alternative to
surcharge may be available. Removal of the upper 10 to 20 feet of spoil will
expose materials that have been compacted by overlying spoils over time. In some
cases, this will be less costly than applying a surcharge because the spoils
that need to be moved must only be handled one time. Of course, this procedure
will lower the ground surface, requiring a disposal location for the excavated
spoils.
Case Study: Fill Stabilization of the Red Onion Maximum-Security Prison
SiteRed Onion Prison is being constructed on a reclaimed mine site at the
border of Wise and Dickenson Counties. The site was originally constructed using
conventional spoil placement procedures. The following text describes procedures
required to stabilize the site as needed to support the prison.
The 16-acre site is a former surface mine that was reclaimed in the late
1980s. Controlled spoil placement and compaction procedures were not employed
during reclamation because the mining company did not expect the site to be used
for building construction. The result was a relatively flat landform that was
perfectly stable, from an environmental standpoint, but was lacking the high
level of structural stability required to support the prison's precast masonry
building units. Depths of spoil under the proposed building location ranged from
30 to 50 feet. A site investigation and geotechnical engineering study conducted
by Schnabel Engineering Associates in 1994 determined that the site's subsurface
provided insufficient support to allow the prison to be constructed effectively.
In 1994, funds were allocated by the Virginia General Assembly to construct
the prison on a portion of 300 acres of land donated to the state by Pittston
Coal Company. The funding included the amount needed to stabilize the site to
support the prison, based on an estimate prepared by Schnabel. Stabilization
consisted of a combination of dynamic compaction and surcharge procedures. Both
procedures were applied because of the maximum security prison project's
sensitivity. In most cases, either one or the other of these two procedures
would have been adequate.
Dynamic CompactionAll building support areas (approximately 8 to 9
acres) were treated with dynamic compaction using weights of 11 and 15 tons
dropped from heights of 25 to 70 feet. The dynamic compaction procedure was
applied to the building site in four passes. Ground conditions determined the
size and shape of the weight used at each location. The first two passes were
conducted as high-energy passes with 15-ton weights on offsetting 15-foot grids
within the building footprint and in all areas located 20 feet or less from the
footprint. The weight was dropped 8 times from a height of 70 feet at each
location. The third pass was also high energy and further compacted mine spoil
beneath the buildings' support footings, with 3 drops per location from a height
of 70 feet. At large column footing locations (5 feet square or larger), 4
points were applied per column, while locations of smaller columns were treated
at a single location per column. The final pass consisted of a low-energy
application covering the entire building footprint using the lighter weight, 25
foot drop, and 2 drops per location.
Several different 15-ton weights were used in the high-energy compaction
procedures. Where the ground was relatively soft (where uncompacted soil-like
materials were present at the surface), a weight exerting 900
pounds-per-square-foot (psf) contact pressure was used; this weight had a 32
square-foot footprint area. Two 1500 psf (20 square-foot) 15-ton weights were
used in areas of rocky or compacted fill.
SurchargeA 15-foot depth of soil and rock materials was applied as
surcharge to areas of the site that will support buildings, and 10 feet of
surcharge was applied to future locations of roadways, parking areas, and
similar facilities. An
area of approximately 10 acres was surcharged. This is slightly larger than the
area that received dynamic compaction - which did not include road and yard
facilities. The surcharge was designed to exert a pressure of about two times
that expected of the completed building; about 250,000 cubic yards of surcharge
material were required. The length of time required of the surcharge for
stabilization to occur was determined by placing settlement plates with
extension rods in the original fill prior to surcharging; these plates were
firmly based in the original fill and extended vertically above the surcharge
fill. Movement of the underlying fill was monitored with reference to the
protruding stancheons. Most areas of the original fill surface moved downward by
1-to-2 inches as a result of the surcharge operation. When the design settlement
had been achieved (3 months, on average, after original placement), the
surcharge was removed.
On some portions of the site, it was necessary to remove more than 15 feet of
existing spoil prior to construction so as to reach final grades. No surcharge
was applied in these areas.
CostsThe cost to prepare the 16-acre prison site for construction was
$8 to 9 million; most of this activity occurred during 1996. About $4 million of
this total covered costs required by the dynamic compaction, surcharge, and
associated procedures. Of these costs, dynamic compaction was responsible for
about $1 million, while surcharge was responsible for about $3 million -
predominantly earth moving costs. The remaining site-preparation costs consisted
of site grading, erosion and sediment control and roadway construction.
Conclusion and SummaryLand use constraints restrict economic
development throughout the Virginia coal mining region, and in adjacent
Appalachian areas. The potential of surface coal mining operations to relieve
this constraint by preparing lands suitable for improved use, although widely
discussed, has not been realized. Experience has shown reclaimed lands suitable
for building sites will often require more than just a flat surface. In order to
minimize postmining settlement within a few years after mining, it is essential
that appropriate spoil placement procedures be utilized in constructing the
building-support fill during reclamation.
Lands reclaimed using conventional practices will often remain subject to
rates of postmining settlement that are considered unacceptable by most land
developers for many building types -- even years after mining. In time,
settlement of these lands will essentially cease -- but in most cases, many
years will be required. It is possible to employ procedures that will accelerate
stabilization of settlement-prone mined lands. However, site-stabilization
procedures do require a considerable expense.
This bulletin contains only general background and guidelines. Both site
stabilization and spoil placement procedures to minimize postconstruction
settlement should be designed in consultation with a professional engineer.
AcknowledgmentsThanks to the following individuals for their help with
this publication: Bob Tuck, Tuck Engineering; Roger Jones, Clinchfield Coal; Ken
Roddenberry, Schnabel Engineering; Gary Dingus, Virginia Cooperative Extension;
Deborah Aylor, Brown, Root Building Company; and retired Virginia Tech Civil
Engineer Bob Krebs.
ReferencesKrebs, R. 1987. Residential Foundations for Reclaimed Land.
Department of Civil Engineering, Virginia Tech.
Krebs, R., and C. Zipper. 1989. Foundations for Housing on Reclaimed Mined
Lands. 12 pages.
Corresponding Author: Carl E. Zipper, Crop and Soil Environmental Sciences,
Virginia Tech, Blacksburg, Virginia 24061-0411. Phone: 540-231-9782. FAX:
540-231-3431. Email: czip@vt.edu
|